PROJECT
Overview
PROJECT CAPACITY:
468 MW
TURBINE:
104 locations utilizing Vestas V163-4.5MW™ turbine technology
SUBSTATION:
The project substation will be located off County Highway E 1300 North Road
COLLECTION:
34.5 kV collector system accompanied with fiber optic cabling
INTERCONNECTION:
Project will be interconnected to the grid through the existing ComEd Mole Creek substation
SITE LOCATION: